The Mississippi Enterprise for Technology's digest of business, science and technology news from NASA's John C. Stennis Space Center, Miss.
Saturday, June 29, 2013
Test stand work awarded
NASA selected Healtheon Inc. of New Orleans to provide a high pressure industrial water line at Stennis Space Center in South Mississippi. The firm-fixed price task order has a total value of $29.8 million and a performance period of 530 days. Work is scheduled to begin in July. The water line provides cooling water and acoustic suppression to Stennis' B Test Complex, which will be used to test the core stage of NASA's Space Launch System in 2016. The work under this task order includes the demolition of all piping systems, including its valves and valve vaults. The contractor also will build a 96-inch diameter high pressure industrial water line from Stennis' High Pressure Industrial Water Plant to the test complex, which spans over a mile. (Source: PRNewswire, 06/28/13)